>
-----Original Message-----
>
From:
Garstang, John
Sent: Friday, February 23, 2001 5:09
PM
> To:
Gerden, Vic Cc:
Vance, Larry; Snow, Eric; Garstang,
Lee
>
Subject:
RE: RCMP Assistance: Sgt. Juby
Importance: High
>
Vic,
> I
noticed that you did not include the
request that Sgt. Juby's move out
of the hangar not commence until
after mid March to facilitate
efficient
completion of work currently in
progress. It may be that you
have
discussed this with Inspector Lathem
and determined that this is not a
problem. If not, I think it is
important to reiterate that if Sgt.
Juby
is instructed to move prior to
completing the work currently in
progress,
I have no confidence that he will
complete this work within the time
we
have requested. The time
estimate I put forward is based on
using the
efficient equipment/production line
setup currently in place in the
hangar, devoting all of Sgt. Juby's
time on these tasks (not on anything
else), not encountering any
significant problems (e.g.
illnesses, etc.),
and allowing Sgt. Juby to directly
work with others in the hangar in
the
manner he does now. Sgt. Juby
has a lot of items in the hangar
setup in a
unique manner, and to disrupt work
now to try and start a move, in
whole
or in part, would be
counterproductive. Just like
us during our move,
Sgt. Juby's two computers may have
to be debugged, etc., with no
guarantees that they will
necessarily work properly at first
try after
being disconnected, transported and
reconnected. I know our people
in the
hangar will try to help (at least to
some extent) if a move starts, out
of
common courtesy, even though we
cannot afford the time to do so.
The RCMP
Identification Office is also
located in Halifax, and just having
to make
one trip from CFB Shearwater to run
back and forth to get something or
to
transport exhibits over the bridges,
through downtown traffic, etc.,
involves a significant amount of
time and effort.
> I
hope that concerns about the move
are a moot point, but I thought I
should point them out just in case
they might have slipped through the
cracks.
>
John
…..
In answer, the following was sent:
From:
"Tom Juby"
<tom.juby@ns.sympatico.ca> To:
"John GARSTANG"
<john.garstang@tsb.gc.ca>
Subject: Time Line for March
Date: Wed, 7 Mar 2001 13:08:04 -0400
John, in answer to you
email of this morning, the following
is offered up as a guideline only:
The
following items are still on my list
of TTD
Mylar/Tedlar examination - Because
of the weather, I have been unable
to put the time into this project
yet, as access to the hangar is
restricted at times due to snow.
This will take two to three days of
work, with timeout to deal with
other minor tasks for photo, etc.
Business Seat examination -
Not started, but again will take one
to two days.
Microtrace Exhibits - Exhibits
to be identified and located,
collected, recorded, and packaged.
This will take at least two days.
Burn
Test Exhibits - Exhibits to be
identified, located, collected,
photographed and exhibited,
recorded, then packaged.
This will take at least two days.
T-Shirt matter - Exhibit to be
retrieved including Customs
paperwork, photography, recording,
sampling, packaging for Microtrace.
At least ½ day.
Wire
Collection for Jim FOOT - Depending
on number of wires, they have to be
located in 'J' Hangar, retrieved,
photographed, recorded, and
packaged. Because of 'J'
Hangar, plan on two hours per
sample.
Photo
processing/Cataloguing - Half
day.
CD
sorting for CAD team - At least one
day over the three weeks.
Exhibit handling for CAD team - At
least one day over the next three
weeks.
The
above list accounts for nearly three
weeks of work (about 14 days), and
that is only if I don't find
anything of interest in the seats or
Mylar.
These
are only ballpark figures, and they
depend on sunny days.
Hope this gives you something to
work with.
This was sent out this afternoon
just after lunch.
The table from yesterday was revised
as follows:
PHOTOS OF 1R DOOR
DEFLECTOR & DRIP SHIELD LOCATION
RCMP/TSB CD #
|
FRAME #
|
AIRCRAFT ID
|
DESCRIPTION
|
DATE OF PHOTOS
|
0514 / 0515
|
40
|
HB-IWE
|
Deflector & Canvas
Shield
|
99-06-25
|
3012 / 3013
|
96-97, 108-109,
113-128
|
HB-IWG
|
Plastic Drip Shield
|
99-06-23
|
3736 / 3736
|
23-24
|
HB-IWM
|
Deflector & Plastic
Shield
|
99-06-22
|
3736 / 3736
|
100
|
HB-1WA
|
Deflector & Plastic
Shield
|
99-06-22
|
3005 / 3004
|
108-111, 130-133
|
HB-IWC
|
Shield in foreground
|
99-06-21
|
1690 / 1688
|
16, 24
|
HB-IWU
|
Deflector, no shield
(removed for D-check?)
|
99-06-16
|
1692 / 1693
|
36, 69-70
59-70
|
HB-IWU
|
Deflector, no shield
(removed?)
|
99-06-16
|
1704 / 1674
|
77-82, 96-102, 122-132
|
HB-IWU
|
Deflector, no shield
(removed?)
|
99-06-15
|
0136 / 0135
|
79, 90-93
|
HB-IWK
|
Deflector, no shield
|
99-03-17
|
2601 / 2602
|
17, 71-85 (Robertson’s
Photos)
|
HB-IWK?
|
Deflector, no shield
|
U/K
|
REVISED 01-03-07
It will be printed off and made
available to Ted tomorrow along with
the CD’s involved.
(Clarification:) The table
shows the aircraft examined that
still retained a protective shield
over the wire run at the forward
right door. The shield had
been ordered removed because it was
redundant. A deflector had
been installed to ensure that the
door didn’t damage the wire runs
when it was raised. However,
it was one of those tasks that need
not be completed until the aircraft
went in for it’s ‘D’ check.
Looking at the aircraft ID’s, one
could easily assume that HB-IWF
(Vaud) still retained the shield.
If so, then this would have been an
ideal location on which to place
incendiary material that would have
created a fire that lasted several
minutes before wires became
involved, thus causing circuits to
short out and fail.
This
shows the black metal deflector in
place without the shield.
This
shows the black metal deflector in
place with a shield or shroud still
in place to its left.